|
INTRODUCTION
CHAPTER ONE - DO WE REALLY HAVE
A PROJECT?
CHAPTER TWO - THE OWNER'S FIRST
STEPS
CHAPTER THREE - SETTLING UPON
A PROJECT DELIVERY METHOD
INTRODUCTION
I. THE TRADITIONAL APPROACH: DESIGN/BID/BUILD
A. The Design
Process
B. The Bidding/Contracting
Phase
C. Build
D. Who Is
Leaving The Traditional Approach And
Why
II. CONSTRUCTION MANAGEMENT
A. Overview
Of Construction Management
B. Construction
Management Responsibilitie
1.
Preconstruction Services
a.
Predesign Services
b.
Design Phase Services
c.
Bid Phase Services
2.
Construction Services
3.
Post Construction Services
C. Should
One Size Fit All?
D. RISK ALLOCATION
IN CONSTRUCTION MANAGEMENT
1.
Introduction
2.
Agency Construction Management
3.
At-Risk Construction Management
III. MULTIPLE PRIME CONTRACTS
A. Overview
Of Multiple Prime Contracts
B. Duty Of
Owner To Coordinate Prime Contractors
1.
Delegation Of Coordination To A Construction
Manager
IV. DESIGN/BUILD
A. Overview
of Design/Build
1.
Variations On The Design/Build Format
2.
Benefits Of The Design/Build Format
a.
Shortening Project Delivery Time:
Fast-Track Construction
b.
Single Source Responsibility 28
c.
No Owner Liability For Design Errors,
But...
3.
The Trade-Off: Loss Of The Design
Professional's Independence
V. FAST TRACK (PHASED) CONSTRUCTION
A. Introduction
B. When Should
Fast Track Be Used?
C. Who Should/Should
Not Use Fast Track?
D. Advantages/Disadvantages
Of Fast Track
CHAPTER FOUR - CHOOSING THE RIGHT
PROJECT PLAYERS
A. Selecting
The Designer
B. Selecting
The Contractor
C. Selecting
The Design/Builder
D. Selecting
The Construction Manager-At-Risk
E. Selecting
The Agency Construction Manager
CHAPTER FIVE - USING THE RIGHT
CONTRACTS WITH EVERY PARTY
A. Avoiding
A Frequent Mistake
B. What Contract
Should Be Used
C. The Agreement
Between The Owner And The Designer
D. The Agreement
Between The Owner And The Contractor
E. The Contract
With The Construction Manager At-Risk
F. The Contract
With The Design/Builder
G. The Contract
With The Agent Construction Manager
CHAPTER SIX - DOTTING THE "I"S
AND CROSSING THE "T"S
A. The Agreement
With The Designer
B. The Agreement
With The Builder
C. If There
Are Performance and Payment Bonds
D. Insurance
Matters
E. Other Checklist
Items At The Time of Contracting
CHAPTER SEVEN - UNDERSTANDING
WHAT YOU HAVE AGREED TO("THE
DEVIL IS IN THE DETAILS")
CHAPTER EIGHT - THE ROLE OF INSURANCE
AND BONDS
A. Insurance
B. Surety
Bonds
CHAPTER NINE - THE OWNER'S ROLE
DURING CONSTRUCTION
A. Concerning
Changes Mandated By The Owner
B. Concerning
Changes Mandated By Designer Mistakes
C. Concerning
Change Caused By Unforeseen Conditions
Or Other Factors
D. Concerning
All Changes
E. At The
Time Of Substantial Completion
CHAPTER TEN - WHEN PROBLEMS ARISE
A. Claims
Brought Against The Owner
1.
Failure To Make Payment
2.
Differing Site Conditions (Also Sometimes
Referred to as Concealed, or Changed
Conditions)
(a).
The Problem
(b).
Ways To Contract Around The Problem
3.
Changes and Requests For Change Orders
(a).
The Two Categories
(b).
Constructive Changes
4.
Paying For Change Orders
5.
Delay and Acceleration
(a).
Generally
(b).
Types Of Delay
(c).
Delay Damages
(d).
Acceleration
(e).
Early Completion
(f).
Defenses To Delay and Acceleration
6.
Wrongful Termination
7.
Responding To The Contractor's Claim
B. CLAIMS
ASSERTED BY THE OWNER
1.
Claims Against The Architect/Engineer
(The "A/E")
(a).
The Cost Estimate
(b).
Lack Of Timeliness
(c).
Defective Or Incomplete Plans Or Specifications
(d).
Inadequate Inspection
(e).
Improper Certifications
2.
Claims Against The Contractor
(a).
Deductive Changes
(b).
Default
(c).
Warranties
(d).
Liquidated Damages
(e).
Actual Damages
(f).
Claims For Breach Of Contract
3.
Claims Against The Construction Manager
4.
Claims Against The Subcontractor
5.
Claims Against The Surety
(a).
Common Acts Of Discharge
(b).
Ways Of Avoiding Discharge
(c).
Guidelines For Preserving The Surety's
Liability
(d)
Options Available To The Surety
(e).
Time Considerations
(f).
Damages Recoverable From The Surety
CHAPTER ELEVEN - PROJECT COMPLETION
AND CLOSEOUT
CHAPTER TWELVE - LIVING WITH THE
COMPLETED PROJECT
APPENDIX A - COMPLETE CHECKLISTS
|